300MW/1200MWh! Polymerized Energy Storage Spurs Yongren Vanadium Flow Energy Storage Power Station Project to be Connected to the Grid in April

during the Qingming Festival, spring is just right, and the upsurge of tackling key problems in the project will not decrease. At the site of the all-vanadium liquid flow energy storage power station project in Yongren County, all the builders of Zhejiang Aggregate Energy Storage Technology Co., Ltd. stuck to their posts during the Qingming Festival holiday, did not stop working and did not relax, seized the golden period of spring construction, and made full efforts to sprint for the key nodes where the first batch of equipment arrived on April 20 and were connected to the grid in April. During the holidays, long queues of transportation vehicles outside the project base, intensive delivery of core equipment, smooth delivery of electrolyte, on-site construction in full swing, press the “fast forward button” for the high-quality promotion of major new energy projects at the provincial level “.

delivery site: traffic flow will not stop to ensure supply

during the Qingming holiday, the yongren production base and the construction site of the project will sprint the progress of the project. all the builders will stick to the front line and are full of heavy trucks loaded with core equipment such as all-vanadium liquid flow reactors, energy storage containers, PCS booster tanks, etc, the road in the park was lined up and sent to the construction site of the power station in turn. In the past two days, the transportation fleet has been stretching, which has become a vivid epitome of the first line of Yongren’s new energy industry construction. The daily equipment delivery volume exceeded 5 sets, fully ensuring that the on-site installation progress did not lag behind.

At the same time, the electrolyte has been successfully put in place and completed all acceptance verification, which has laid a key foundation for subsequent system injection and joint commissioning, marking another solid step towards the goal of putting the project into production and grid connection.

in order to ensure the timely, safe and efficient delivery of equipment, we will gather energy storage joint partners, set up a special guarantee and supply team, optimize the connection of the whole process of production, quality inspection, loading and transportation, reasonably coordinate the holiday construction arrangements, strictly abide by the bottom line of safety and quality, efficiently promote the landing of various tasks, and ensure that each batch of equipment is strictly tested, accurately loaded and delivered on time. The person in charge of the site said that the current is a critical window period for project construction. All personnel stick to their posts, race against time, fight on the wall chart, make every effort to ensure that the equipment supply is not out of touch, the site installation is not stopped, and resolutely hold the established node target.

project speed up: sprint to ensure nodes

yongren 300MW/1200MWh all-vanadium liquid flow energy storage power station is a key new energy benchmark project in Yunnan province, with a total investment of 3.382 billion yuan. upon completion, it will become the leading long-term energy storage power station in China, it is of great significance to help the transformation of regional energy structure, improve the peak regulation capacity of power grid and ensure the safe and stable operation of power grid. At present, the project has entered the core stage of centralized arrival of equipment and on-site installation. various construction tasks are carried out simultaneously and efficiently:

energy storage field area: 100 of battery compartment foundation construction is completed;

booster station: 220kV main equipment installation and commissioning has entered the final stage, gradually meeting the charging conditions;

integrated production line: yongren 500MW/2GWh integrated production line operates efficiently at full load, with daily delivery of 5 sets, 2.5MW/10MWh;

• Electrolyte guarantee: the electrolyte is fully in place to fully meet the requirements of subsequent system injection and debugging.

Aggregate Energy Storage Chairman Zheng Xiangyu said that the project has been included in the provincial list of major projects, with a heavy responsibility and mission on the shoulder. During the Qingming holiday, all the builders took the responsibility with hard work, stuck to their posts to overcome difficulties, always insisted on rushing to schedule, ensuring quality, and keeping safety, and made every effort to ensure that the goal of grid connection was achieved on schedule, and the development of Yongren’s new energy industry and Yunnan’s new power system Construction contributes to aggregation.

government-enterprise coordination: focus on tackling key problems and build a benchmark

the whole process of project construction has received full support from Yongren county party Committee, county government and relevant departments. Before and after the Qingming holiday, the county leaders went deep into the project site investigation and supervision for many times, actively coordinated and solved practical problems such as transportation, land use guarantee, power matching, etc., opened up a “green channel” for project construction, and provided service guarantee throughout the process. Jinjiang Energy, China Construction Third Bureau and other participating units work together and cooperate closely to form a good construction pattern of “multi-party coordination and efficient promotion.

The relevant person in charge of Yongren County said that Yongren is making every effort to build an important energy storage industry base in Yunnan, and the aggregate energy storage project is the core support for the development of the county’s new energy industry. In the next step, the local government will continue to optimize the business environment, ensure the whole process of service, help the project to complete grid-connected power generation as soon as possible, and promote Yongren’s green and low-carbon transformation and high-quality economic development.

looking forward to the future: energy storage empowers to go to a new journey

from the builders who stick to the front line during the Qingming holiday, to the equipment delivery site where traffic is endless, and to the smooth arrival of thousands of cubic meters of electrolyte, everywhere demonstrates the practical spirit of the project team to overcome difficulties and forge ahead together. With the steady progress of various key links, the project is about to usher in a key leap from construction to grid connection. In the future, it will provide a solid guarantee for the consumption of clean energy in Yunnan and the safe and stable operation of the power grid. It will also inject strong green momentum into the landing of the national “double carbon” goal.