600MW/1.2GWh! Ningxia a number of shared energy storage power station energy storage equipment bidding!

On April 9, 2026, public bidding for the procurement of energy storage equipment for three shared energy storage power station projects in Ningxia, with a total scale of 600MW/1.2GWh.

the scale of the shared energy storage power station project of Ningxia chuangneng technology co., ltd., the shared energy storage power station project of Ningxia anchuang energy technology co., ltd. and the shared energy storage power station project of Ningxia tanwei energy technology co., ltd. are all 200MW/400MWh. the reserved interface and technical conditions for subsequent expansion to 200MW/800MWh need to be considered. the 1500V energy storage system design scheme, and grid-connected.

the bidding scope includes the supply of equipment required for the energy storage system and the guidance of installation, equipment commissioning, cooperation with completion acceptance, and coordination of grid connection acceptance procedures.

All projects require bidders to have a cumulative performance of not less than 5GWh energy storage system integration in China within three years, and none of them will accept consortium bids.

The text reads as follows:

Ningxia chuangneng technology co., ltd. 200MW/400MWh shared energy storage power station project-bidding announcement for energy storage system equipment procurement

1. bidding conditions

this bidding project Ningxia chuangneng technology co., ltd. 200MW/400MWh shared energy storage power station has been approved by Zhongning county development and reform bureau to Ningxia autonomous region enterprises investment project record certificate, project code: 2411-640521-60-01-345852 approved for construction. The construction funds are raised by the enterprise itself. The tenderer is Ningxia Chuangneng Technology Co., Ltd. The project has already met the bidding conditions, and the procurement of energy storage system equipment for the project is now subject to public bidding.

Ningxia Hongde Yihe Engineering Consulting Co., Ltd. is entrusted by the tenderee to be responsible for the bidding of this project.

2. project overview and bidding scope

2.1 project overview:

Ningxia chuangneng technology co., ltd. 200MW/400MWh shared energy storage power station is located in qukou farm, zhongning county, zhongwei city, Ningxia Hui autonomous region, and Ningxia chuangneng technology co., ltd. 200MW/400MWh shared energy storage power station, the equipment supply for this tender needs to consider the reserved interface and technical conditions for subsequent expansion to 200MW/800MWh.

2.2 bidding scope:

including but not limited to Ningxia chuangneng technology co., ltd. 200MW/400MWh shared energy storage power station energy storage system equipment manufacturing, pre-factory testing, packaging, transportation, on-site delivery, etc. Product quantity, technical specifications and requirements shall be subject to the technical specifications of the bidding documents. (see the technical specifications for details)

(1) the scope of this tender is the supply of equipment required for the energy storage system and the guidance of installation, equipment commissioning, cooperation with completion acceptance, and coordination of grid connection acceptance procedures, etc, including but not limited to energy storage system battery cluster, PCS, EMS, dry-type transformer, DC bus equipment, container and supporting facilities in the box (such as temperature control, ventilation pipe, power distribution, fire protection, security, lighting, materials, etc, at the same time, consider the fire retardant requirements), energy storage system equipment between cables and communication cables and other equipment and equipment components within the scope of supply selection, design, manufacturing, provision of drawings, factory test, supply, packaging, shipment, on-site delivery, installation guidance, on-site commissioning, performance test, coordination handover test, coordination with relevant units acceptance, etc. The field equipment handover test shall be completed by the Tenderee, and the Bidder shall cooperate.

The battery cluster includes energy storage batteries, battery insertion boxes, battery management systems (hereinafter referred to as BMS) and battery racks, high-voltage boxes, supporting accessories and DC cables. The energy storage battery uses a new lithium iron phosphate battery.

In addition, the Bidder shall provide drawings related to the energy storage system, including but not limited to the layout of each equipment of the energy storage system, electrical connection diagram, communication system diagram and other drawings within the scope of supply.

This tender adopts the design scheme of 1500V energy storage system, and the grid-connected voltage level is 35kV.

(2) The cables and accessories between the 35kV high-voltage side of the energy storage system and the parallel network point in this project shall be provided, laid and installed by the tenderee.

primary demarcation point: the cables and accessories (including terminals) between the equipment in the container of the energy storage system and between the container and the container shall be provided by the bidder, the cables and accessories between the energy storage system and the equipment supplied by other manufacturers of the tenderee shall be provided by the tenderee, and the tenderee shall be responsible for the laying, wiring and system debugging and other work of all cables.

secondary demarcation point: the cables, communication cables and accessories between the energy storage system equipment supplied by the bidder shall be provided by the bidder, the cables and accessories between the energy storage system and the equipment supplied by other manufacturers of the tenderee shall be provided by the tenderee, and the tenderee shall be responsible for laying, wiring and system debugging and other work of all cables.

commissioning boundary: the bidder shall, in accordance with the requirements of local government departments and local power grid companies, cooperate with the completion acceptance, cooperate with the tenderee to complete the fire control acceptance, cooperate with the coordination of the grid connection acceptance procedures, etc., and the acceptance cost shall be borne by the tenderee.

2.3 place of delivery: the place designated by the tenderee of the 200MW/400MWh shared energy storage power station project of Ningxia chuangneng technology co., ltd.

2.4 delivery method: delivery at the designated place of the tenderee on the project site.

2.5 delivery time: 150 days, starting from May 4, 2026 and completing all equipment delivery on September 30, 2026.

Note: The work period in the bid opening list refers to the delivery date, I .e. the planned delivery time of the first batch of equipment is 5 days after the signing of the contract. The delivery schedule during the delivery period must be continuously balanced and meet the requirements of on-site construction schedule. The specific delivery batch and quantity shall be subject to the notice of the tenderee. The tenderee has the right to adjust the delivery time according to the actual progress of the project, and the bidder shall not require to adjust the contract price accordingly.

2.6 contract signing method:

the bidding equipment (materials) is the equipment content of “EPC general contract for 200MW/400MWh shared energy storage power station project of Ningxia chuangneng technology co., ltd.” the construction unit shall be the bidding subject and the winning bidder shall be determined. The EPC general contractor, as the purchaser, signs the supply contract with the winning equipment manufacturer and pays the contract price, and completes the arrival, storage, installation and commissioning of the corresponding equipment (materials).

3. qualification requirements for bidders

3.1 general qualification conditions

3.1.1 bidders are independent legal persons or other organizations legally registered within the territory of the People’s Republic of China, with independent capacity to bear civil liability and the right to independently conclude contracts;

3.1.2 the bidder shall meet the following conditions in terms of finance and reputation:

(1) not in the process of being ordered to stop production, suspend business or enter into bankruptcy proceedings, the production and operation are normal and have the ability to perform the contract (commitment is required);

(2) not in the penalty period of prohibition of bidding confirmed by the administrative department (commitment is required) or relevant documents;

(3) in the past three years, there has been no fraudulent winning of the bid or serious breach of contract, and there has been no major or above quality accident or major or above safety accident caused by its products, construction or services identified by relevant departments (commitment is required);

(4) not listed on the credit China website as the subject of breach of trust and major tax violations and breach of trust. Except those who have been removed from the list before the deadline for submission of bids. (“China Executive Information Disclosure Network” and “Credit China” websites (commitments and screenshots of website inquiries are required);

(5) Legal persons, other organizations or individuals that have an interest relationship with the tenderee and may affect the fairness of the bidding are not allowed to participate in the bidding. The person in charge of the unit is the same person or different units with holding and management relationships, it is not allowed to participate in the bidding of the same bidding project in the same bid section or not divided into bid sections (commitment is required).

Note: Bidders who fail to provide screenshots of website queries as required by clause (4) above will be rejected.

special qualification conditions for 3.2

3.2.1 the bidder must have the research and development and manufacturing capability of at least one core product in the main components of electrochemical energy storage system products (batteries, PCS, EMS), and provide corresponding certification documents (provide CNAS or CGC or CQC and other third-party certification certificates or test reports to prove that the product is developed or manufactured by the bidder).

3.2.2 the bidder has CNAS or CGC or CQC certification report and provides relevant certification documents of the equipment used in this bid; The battery and module must have a type certification report issued by a national certification authority that meets the requirements of GB/T36276-2023.

3.2.3 the bidder has accumulated not less than 5 GWh energy storage system integration performance in China since January 1, 2023 (subject to the time of signing the contract) (the performance certification documents must fully reflect the key contents such as the name, project name and signature, equipment name, specification capacity, signing date, etc. of both parties to the supply contract, and at least one contract performance invoice shall be provided for each contract).

3.3 this tender does not accept the consortium bid, the person in charge of the unit for the same person or the existence of holding, management relationship of different units, may not participate in the tender project tender at the same time.

3.4 This project does not accept agents to bid.

3.5. this tender adopts the method of post-qualification examination. after the bid opening, the bid evaluation committee will examine the qualification of the bidder. if the qualification conditions do not meet the requirements stipulated in the tender documents, the bid evaluation committee will reject the bid.

Ningxia anchuang energy technology co., ltd. 200MW/400MWh shared energy storage power station project-bidding announcement for energy storage system equipment procurement

1. bidding conditions

this bidding project Ningxia anchuang energy technology co., ltd. 200MW/400MWh shared energy storage power station has been invested by Zhongning county development and reform bureau in Ningxia Hui autonomous region enterprises filing certificate, project code: 2411-640521-60-01-953057 approved for construction. The construction fund is raised by the enterprise itself. The tenderer is Ningxia Anchuang Energy Technology Co., Ltd. The project has already met the bidding conditions, and the procurement of energy storage system equipment for the project is now subject to public bidding.

Ningxia Hongde Yihe Engineering Consulting Co., Ltd. is entrusted by the tenderee to be responsible for the bidding of this project.

2. project overview and bidding scope

2.1 project overview:

Ningxia anchuang energy technology co., ltd. 200MW/400MWh shared energy storage power station is located in qukou farm, zhongning county, zhongwei city, Ningxia Hui autonomous region, and Ningxia anchuang energy technology co., ltd. 200MW/400MWh shared energy storage power station, the equipment supply for this tender needs to consider the reserved interface and technical conditions for subsequent expansion to 200MW/800MWh.

the scope of 2.2 bidding:

includes but is not limited to the manufacturing, pre-factory testing, packaging, transportation, on-site delivery of energy storage system equipment of 200MW/400MWh shared energy storage power station of Ningxia anchuang energy technology co., ltd. Product quantity, technical specifications and requirements shall be subject to the technical specifications of the bidding documents. (see the technical specifications for details)

(1) the scope of this tender is the supply of equipment required for the energy storage system and the guidance of installation, equipment commissioning, cooperation with completion acceptance, and coordination of grid connection acceptance procedures, etc, including but not limited to energy storage system battery cluster, PCS, EMS, dry-type transformer, DC bus equipment, container and supporting facilities in the box (such as temperature control, ventilation pipe, power distribution, fire protection, security, lighting, materials, etc, at the same time, consider the fire retardant requirements), energy storage system equipment between cables and communication cables and other equipment and equipment components within the scope of supply selection, design, manufacturing, provision of drawings, factory test, supply, packaging, shipment, on-site delivery, installation guidance, on-site commissioning, performance test, coordination handover test, coordination with relevant units acceptance, etc. The field equipment handover test shall be completed by the Tenderee, and the Bidder shall cooperate.

The battery cluster includes energy storage batteries, battery insertion boxes, battery management systems (hereinafter referred to as BMS) and battery racks, high-voltage boxes, supporting accessories and DC cables. The energy storage battery uses a new lithium iron phosphate battery.

In addition, the Bidder shall provide drawings related to the energy storage system, including but not limited to the layout of each equipment of the energy storage system, electrical connection diagram, communication system diagram and other drawings within the scope of supply.

This tender adopts the design scheme of 1500V energy storage system, and the grid-connected voltage level is 35kV.

(2) The cables and accessories between the 35kV high-voltage side of the energy storage system and the parallel network point in this project shall be provided, laid and installed by the tenderee.

primary demarcation point: the cables and accessories (including terminals) between the equipment in the container of the energy storage system and between the container and the container shall be provided by the bidder, the cables and accessories between the energy storage system and the equipment supplied by other manufacturers of the tenderee shall be provided by the tenderee, and the tenderee shall be responsible for the laying, wiring and system debugging and other work of all cables.

secondary demarcation point: the cables, communication cables and accessories between the energy storage system equipment supplied by the bidder shall be provided by the bidder, the cables and accessories between the energy storage system and the equipment supplied by other manufacturers of the tenderee shall be provided by the tenderee, and the tenderee shall be responsible for laying, wiring and system debugging and other work of all cables.Debugging Boundary: The Bidder shall, in accordance with the requirements of local government authorities and the local power grid company, cooperate with the completion acceptance, assist the Employer in completing the fire safety acceptance, and facilitate and coordinate the procedures for obtaining approval of the grid-connection acceptance. The costs associated with these acceptance activities shall be borne by the Employer.

2.3 place of delivery: the place designated by the tenderee of the 200MW/400MWh shared energy storage power station project of Ningxia anchuang energy technology co., ltd. 2.4 Delivery Method: Delivery to the location designated by the Tenderer at the project site. 2.5 Delivery Period: 150 days, with the first delivery scheduled for May 4, 2026, and completion of all equipment deliveries by September 30, 2026. Note: In the bid opening summary table, the project duration refers to the delivery period. Specifically, the first batch of equipment is scheduled for delivery within 5 days after the contract is signed. Delivery progress during the specified delivery period must be continuous and balanced, and it must align with the on-site construction schedule. The specific delivery batches and quantities shall be subject to notification by the tendering party. The tendering party reserves the right to adjust the delivery schedule based on the actual progress of the project. Bidders shall not, on this ground, request an adjustment to the contract price.

2.6 contract signing method:

the bidding equipment (materials) is the equipment content of “EPC general contract for 200MW/400MWh shared energy storage power station project of Ningxia anchuang energy technology co., ltd.” the construction unit shall be the bidding subject and the winning bidder shall be determined. Contract performance shall be carried out by the EPC general contractor, which, as the purchaser, will enter into supply contracts with the winning equipment manufacturers and make payments of the contract price. The contractor will also be responsible for the arrival, storage, installation, commissioning, and other related tasks associated with the supplied equipment (materials).

3. qualification requirements for bidders

3.1 general qualification conditions

3.1.1 bidders are independent legal persons or other organizations legally registered within the territory of the People’s Republic of China, with independent capacity to bear civil liability and the right to independently conclude contracts;

3.1.2 the bidder shall meet the following conditions in terms of finance and reputation:

(1) not in the process of being ordered to stop production, suspend business or enter into bankruptcy proceedings, the production and operation are normal and have the ability to perform the contract (commitment is required);

(2) not in the penalty period of prohibition of bidding confirmed by the administrative department (commitment is required) or relevant documents;

(3) in the past three years, there has been no fraudulent winning of the bid or serious breach of contract, and there has been no major or above quality accident or major or above safety accident caused by its products, construction or services identified by relevant departments (commitment is required);

(4) not listed on the credit China website as the subject of breach of trust and major tax violations and breach of trust. Except for those that have already been removed from the list before the bid submission deadline. (“China Execution Information Disclosure Website” and the “Credit China” website; a commitment letter must be provided, along with screenshots of the website searches);

(5) Any legal entity, other organization, or individual that has a conflict of interest with the tenderer and may therefore compromise the fairness of the tendering process shall not participate in the bidding. Different entities whose heads are the same person, or between which there exists a controlling or managerial relationship, shall not both bid for the same lot, nor shall they both bid for the same tender project where no lots have been defined (a commitment letter must be provided). Note: Bids will be disqualified if the bidder fails to provide the website query screenshots as required in paragraph (4) above.

3.2 Specific Qualification Requirements

3.2.1 Bidders shall possess R&D and manufacturing capabilities for at least one core component of electrochemical energy storage system products (battery cells, PCS, EMS), and shall provide supporting documentation (e.g., third-party certification certificates or test reports issued by CNAS, CGC, CQC, or similar organizations) to demonstrate that the relevant product was developed or manufactured by the bidder.

3.2.2 The bidder shall possess reports certified by CNAS, CGC, or CQC and provide relevant supporting documents for the equipment used in this bid. Batteries and battery modules must be accompanied by type-certification reports issued by a nationally accredited authoritative body, demonstrating compliance with the requirements of GB/T 36276-2023. 3.2.3 From January 1, 2023, to the present (as determined by the contract signing date), the Bidder shall have cumulatively completed energy storage system integration projects within China with a total capacity of no less than 5 GWh. The supporting documentation must clearly and comprehensively reflect the names of both parties to the supply contract, the project name and official seals, the equipment names and specifications/capacities, and the contract signing date. At least one invoice evidencing contract performance shall be provided for each contract. 3.3 This tender does not accept joint venture bids. Entities with the same legal representative or those that have a controlling or management relationship with one another shall not simultaneously participate in this tender. 3.4 This project does not accept bids from agents. 3.5. This tender will be evaluated using a post-qualification review process. Following the opening of bids, the Evaluation Committee will examine the bidders’ qualifications. If a bidder fails to meet the qualification requirements specified in the Tender Documents, its bid will be rejected by the Evaluation Committee.

Ningxia exploration energy technology co., ltd. 200MW/400MWh shared energy storage power station project-bidding announcement for energy storage system equipment procurement

1. bidding conditions

this bidding project Ningxia exploration energy technology co., ltd. 200MW/400MWh shared energy storage power station has been invested by Zhongning county development and reform bureau in Ningxia autonomous region enterprises filing certificate, project code: 2411-640521-60-01-848722 approved for construction. The construction fund is raised by the enterprise itself. The tenderer is Ningxia Tanwei Energy Technology Co., Ltd. The project now meets the conditions for tendering. An open tender is hereby announced for the procurement of energy storage system equipment for this project. Ningxia Hongde Yihhe Engineering Consulting Co., Ltd., entrusted by the procuring entity, is responsible for the tendering procedures of this project.

2. project overview and bidding scope

2.1 project overview:

Ningxia tanwei energy technology co., ltd. 200MW/400MWh shared energy storage power station is located in qukou farm, zhongning county, zhongwei city, Ningxia Hui autonomous region, and Ningxia tanwei energy technology co., ltd. 200MW/400MWh shared energy storage power station, the equipment supply for this tender needs to consider the reserved interface and technical conditions for subsequent expansion to 200MW/800MWh.

the scope of 2.2 bidding:

includes but is not limited to the manufacturing, pre-factory testing, packaging, transportation, on-site delivery of energy storage system equipment for 200MW/400MWh shared energy storage power station of Ningxia tanwe energy technology co., ltd. The quantity of products, technical specifications, and requirements shall be governed by the Technical Specifications document in the tender documentation. (see the technical specifications for details)

(1) the scope of this tender is the supply of equipment required for the energy storage system and the guidance of installation, equipment commissioning, cooperation with completion acceptance, and coordination of grid connection acceptance procedures, etc, including but not limited to energy storage system battery cluster, PCS, EMS, dry-type transformer, DC bus equipment, container and supporting facilities in the box (such as temperature control, ventilation pipe, power distribution, fire protection, security, lighting, materials, etc, at the same time, consider the fire retardant requirements), energy storage system equipment between cables and communication cables and other equipment and equipment components within the scope of supply selection, design, manufacturing, provision of drawings, factory test, supply, packaging, shipment, on-site delivery, installation guidance, on-site commissioning, performance test, coordination handover test, coordination with relevant units acceptance, etc. The on-site equipment handover tests shall be conducted by the tenderer, with cooperation from the bidder.

The battery cluster comprises energy-storage batteries, battery plug-in cabinets, a battery management system (hereinafter referred to as BMS), a battery rack, a high-voltage switchgear cabinet, accompanying accessories, and DC cables. The energy storage battery uses a new lithium iron phosphate battery. In addition, the bidder shall provide drawings related to the energy storage system, including but not limited to equipment layout plans, electrical connection diagrams, communication system diagrams, and other drawings within the scope of supply. This tender calls for a 1,500V energy storage system design, with a grid-connection voltage level of 35 kV.

(2) In this project, the 35kV high-voltage side cables and associated accessories connecting the energy storage system to the grid connection point shall be provided, laid, and installed by the tenderer. One demarcation point: Cables and accessories (including terminations) between equipment within the energy storage system containers, as well as between containers, shall be provided by the bidder. Cables and accessories connecting the energy storage system to equipment supplied by other vendors of the tenderer shall be provided by the tenderer. The tenderer shall be responsible for all cable laying, wiring, system commissioning, and other related work. Second demarcation point: The bidder shall supply all cables, communication cables, and associated accessories between the energy storage system equipment supplied by the bidder. Cables and accessories connecting the energy storage system to equipment supplied by other vendors engaged by the tenderer shall be provided by the tenderer. The tenderer shall be responsible for all other works, including cable laying, wiring, and system commissioning. Debugging Boundary: The Bidder shall, in accordance with the requirements of local government authorities and the local power grid company, cooperate with the completion acceptance, assist the Employer in completing the fire safety acceptance, and facilitate and coordinate the procedures for obtaining approval of the grid-connection acceptance. The costs associated with these acceptance activities shall be borne by the Employer.

2.3 place of delivery: the place designated by the tenderee of the 200MW/400MWh shared energy storage power station project of Ningxia towi energy technology co., ltd. 2.4 Delivery Method: Delivery to the location designated by the Tenderer at the project site.

2.5 delivery time: 143 days, starting from May 11, 2026 and completing all equipment delivery on September 30, 2026. Note: In the bid opening summary table, the project duration refers to the delivery period. Specifically, the first batch of equipment is scheduled for delivery within 5 days after the contract is signed. Delivery progress during the specified delivery period must be continuous and balanced, and it must align with the on-site construction schedule. The specific delivery batches and quantities shall be subject to notification by the tendering party. The tendering party reserves the right to adjust the delivery schedule based on the actual progress of the project. Bidders shall not, on this ground, request an adjustment to the contract price.

2.6 contract signing method:

the equipment (materials) for this tender is the equipment content of “EPC general contract for 200MW/400MWh shared energy storage power station project of Ningxia exploration and development energy technology co., ltd.” the construction unit shall be the main body of the tender and the winning bidder shall be determined. Contract performance shall be carried out by the EPC general contractor, which, as the purchaser, will enter into supply contracts with the winning equipment manufacturers and make payments of the contract price. The contractor will also be responsible for the arrival, storage, installation, commissioning, and other related tasks associated with the supplied equipment (materials).

3. qualification requirements for bidders

3.1 general qualification conditions

3.1.1 bidders are independent legal persons or other organizations legally registered within the territory of the People’s Republic of China, with independent capacity to bear civil liability and the right to independently conclude contracts;

3.1.2 the bidder shall meet the following conditions in terms of finance and reputation:

(1) not in the process of being ordered to stop production, suspend business or enter into bankruptcy proceedings, the production and operation are normal and have the ability to perform the contract (commitment is required);

(2) not in the penalty period of prohibition of bidding confirmed by the administrative department (commitment is required) or relevant documents;

(3) in the past three years, there has been no fraudulent winning of the bid or serious breach of contract, and there has been no major or above quality accident or major or above safety accident caused by its products, construction or services identified by relevant departments (commitment is required);

(4) not listed on the credit China website as the subject of breach of trust and major tax violations and breach of trust. Except for those that have already been removed from the list before the bid submission deadline. (“China Execution Information Disclosure Website” and the “Credit China” website; a commitment letter must be provided, along with screenshots of the website searches);

(5) Any legal entity, other organization, or individual that has a conflict of interest with the tenderer and may therefore compromise the fairness of the tendering process shall not participate in the bidding. Different entities whose heads are the same person, or between which there exists a controlling or managerial relationship, shall not both bid for the same lot, nor shall they both bid for the same tender project where no lots have been defined (a commitment letter must be provided). Note: Bids will be disqualified if the bidder fails to provide the website query screenshots as required in paragraph (4) above.

3.2 Specific Qualification Requirements

3.2.1 Bidders shall possess R&D and manufacturing capabilities for at least one core component of electrochemical energy storage system products (battery cells, PCS, EMS), and shall provide supporting documentation (e.g., third-party certification certificates or test reports issued by CNAS, CGC, CQC, or similar organizations) to demonstrate that the relevant product was developed or manufactured by the bidder.

3.2.2 The bidder shall possess reports certified by CNAS, CGC, or CQC and provide relevant supporting documents for the equipment used in this bid. Batteries and battery modules must be accompanied by type-certification reports issued by a nationally accredited authoritative body, demonstrating compliance with the requirements of GB/T 36276-2023. 3.2.3 From January 1, 2023, to the present (as determined by the contract signing date), the Bidder shall have cumulatively completed energy storage system integration projects within China with a total capacity of no less than 5 GWh. The supporting documentation must clearly and comprehensively reflect the names of both parties to the supply contract, the project name and official seals, the equipment names and specifications/capacities, and the contract signing date. At least one invoice evidencing contract performance shall be provided for each contract. 3.3 This tender does not accept joint venture bids. Entities with the same legal representative or those that have a controlling or management relationship with one another shall not simultaneously participate in this tender. 3.4 This project does not accept bids from agents. 3.5. This tender will be evaluated using a post-qualification review process. Following the opening of bids, the Evaluation Committee will examine the bidders’ qualifications. If a bidder fails to meet the qualification requirements specified in the Tender Documents, its bid will be rejected by the Evaluation Committee.