on April 8, Baotou Jiuyuan green hydrogen synthetic ammonia urea project was filed.
figure: project filing announcement
announcement shows that the project unit is Nanjing tianga energy technology co., ltd. and the construction site is Jiuyuan industrial park in Baotou, inner Mongolia. With a total investment of 453 million yuan, the project is planned to start in December 2026 and be completed in September 2028.
The project area is about 100 mu, of which the production plant is expected to occupy about 80 mu. Construction content: including 100000 tons/year ammonia synthesis plant, liquid ammonia storage tank, 175000 tons/year urea synthesis plant, CCUS plant, office building, ancillary facilities, etc.