On April 8, Honghe Prefecture, Yunnan Province, issued an announcement on the cancellation of the “Announcement on the Selection of 34 New Energy Project Owners in the Construction List of the Third Batch of New Energy Projects in Yunnan Province in 2025.
According to the announcement, the publicity has problems such as procedural convergence that needs to be further improved. In order to ensure the fairness, impartiality and standardization of the project selection work, it is decided to cancel the publicity of the selection. The follow-up work will be re-organized and publicized in accordance with laws and regulations after completing the internal audit and reporting to the Honghe Prefecture People’s Government for approval.
It is understood that on March 20, the People’s Government of Honghe Prefecture issued the ”Honghe Prefecture is included in the list of the third batch of new energy projects in Yunnan Province in 2025. The public announcement of the selection of 34 new energy project construction owners “. The total number of scenic projects announced this time is 2224MW, including 12 photovoltaic projects with a total scale of 660MW. There are 22 wind power projects with a total scale of 1564MW, with a planned investment of 7.038 billion yuan.
for the original text, see below:
on the cancellation of the announcement of the selection of 34 new energy project construction owners listed in the list of the third batch of new energy projects in Yunnan province in 2025
entrusted by honghe state energy bureau, honghe Prefecture Construction Engineering Tendering Co., Ltd. on March 20, 2026 on the Honghe Prefecture People’s Government portal (.cn) released the “Honghe Prefecture included in the list of the third batch of new energy projects in Yunnan Province in 2025 the construction of 34 new energy projects in the construction of the owner of the selection of the work of the public.”
After verification, the publicity has problems such as procedural convergence that needs to be further improved. In order to ensure the fairness, impartiality and standardization of the project selection work, it is decided to cancel the publicity of the selection. The follow-up work will be re-organized and publicized in accordance with laws and regulations after completing the internal audit and reporting to the Honghe Prefecture People’s Government for approval.
It is hereby announced.
client: honghe state energy bureau
contact: pan chun
tel: 0873-390760
agency: honghe state construction engineering tendering co., ltd.
contact: Hou jianwei
tel: 0873-3038448
April 8, 2026