On April 2, the Zhenjiang Municipal Development and Reform Commission issued the “Distributed Photovoltaic Power Generation Project Grid Connection Process (Draft for Comment)”. In terms of the grid-connected service process for the construction of distributed photovoltaic projects, provisions have been made in six major aspects, including improving filing management, grid-connected intention reply, on-site investigation, acceptance and reply of access system design plan report, signing of contract agreement, installation of metering devices and grid-connected inspection, and electricity bill settlement. The main points are as follows:
· improve the record management
the record information of distributed photovoltaic power generation project shall include the project name, investment subject, construction site, project type, construction scale, Internet access mode, etc. For providing false information, the filing authority may deal with it in accordance with the relevant provisions. For projects that do not conform to the actual situation on site or the filing information and relevant policies, the power supply enterprise shall remind the user to modify the filing information in time. If the user refuses to modify or fails to provide the correct filing certificate within the time limit, the power supply enterprise shall not connect to the grid and terminate the business.
· reply to grid connection intention
within the same red line of land use, industrial and commercial distributed photovoltaic power generation projects constructed by stages shall not add new connection points with the public power grid. For projects constructed in phases and filed separately by the same investor, in principle only one power generation account shall be established. For projects constructed in phases and filed separately by different investors, one power generation account may be established; alternatively, separate accounts may be opened after the relevant investors have reached a mutually agreed arrangement for the allocation of generated electricity. In the acceptance and network intention forward, power supply enterprises should focus on the examination of the nature of household distributed photovoltaic property rights, in strict accordance with the nature of property rights classification disposal.
· site investigation
if the project starts construction ahead of schedule, the power supply enterprise shall suspend the acceptance of its intention to connect to the grid and report the relevant information to the local competent department.
-Accepting and replying to the report of the design scheme of the access system
for the distributed photovoltaic power generation project for natural households, the power supply enterprise directly replies to the owner of the distributed photovoltaic power generation project according to the typical design scheme.
, contract agreement signing, metering device installation and grid connection inspection
before the distributed photovoltaic power generation project is connected to the grid, the power supply enterprise shall be responsible for the acceptance of the user side lines (cables), grid connection switches, power distribution devices, high-voltage electric energy metering devices, inverters, capacitors, lightning arresters, other electrical equipment test results and operator qualifications. for those who fail the completion acceptance, the project investment entity shall complete the rectification within 4 working days. If the rectification is not completed within the prescribed time limit, the power supply enterprise shall not be connected to the grid.
· electricity bill settlement
distributed photovoltaic power generation projects and power supply enterprises must sign electricity purchase and sale contracts before carrying out electricity bill settlement. if no electricity contract is signed, electricity bill settlement shall not be carried out. The cost of electricity generated by the distributed photovoltaic power generation project shall be paid by the main body of the power supply contract. If the payment is not made within the time limit, the power supply enterprise may implement the power outage due in accordance with the law and disconnect the connection point between the photovoltaic project and the power grid side.
the original text is as follows:
notice on publicly soliciting opinions on the grid connection process of distributed photovoltaic power generation projects (draft for comments)
in order to further promote the safe and healthy development of distributed photovoltaic power generation, standardize the grid connection process of distributed photovoltaic power generation, the Municipal Development and Reform Commission, together with the State Grid Zhenjiang Power Supply Company, drafted the “Distributed Photovoltaic Power Generation Project Grid-connected Process (Draft for Comments)”. We are now soliciting opinions from the public. If there are any amendments and suggestions, please feedback them to the Energy Department of the Municipal Development and Reform Commission before May 6, 2026, email address: zjjwnyc@126.com, telephone number: 0511-80902126.
Zhenjiang Development and Reform Commission
April 2, 2026
distributed photovoltaic power generation project grid connection process
(draft for public comments)
distributed photovoltaic power generation project applies for grid connection, the project construction unit or individual shall submit an application to the power supply enterprise according to the following procedures and go through the relevant grid connection procedures.
1. applicants to submit application materials
1. natural person household distributed photovoltaic power generation projects shall provide the applicant’s valid identity certificate, power generation address ownership certificate (real estate certificate, land certificate or homestead certificate, housing property right certificate issued by township and above governments, etc.), “letter of intent for grid connection of distributed photovoltaic power generation projects”, project filing certificate (projects filed by the centralized agent of the power supply enterprise do not need to provide), “natural person household distributed photovoltaic project self-investment commitment letter” and other information.
2. non-natural person household, general industrial and commercial, large-scale industrial and commercial photovoltaic power generation projects should provide the project investment subject business license, power generation address ownership certificate, “distributed photovoltaic power generation project grid-connected letter of intent”, project filing documents, project preliminary work progress and other application materials. For projects constructed on non-proprietary premises, a contract energy management agreement or a power generation site lease agreement must also be provided. If the application is handled by an agent, the agent’s valid identification and a letter of authorization must be submitted as well.
3. other scenarios
(1) for the use of residential buildings (excluding independent villas) public parts of the construction of distributed photovoltaic projects, should provide the property and the owners committee (or all owners of residential buildings) agreed to the construction of proof materials.
(2) the use of village collective or neighborhood committee owned and public office buildings and other buildings (excluding ancillary sites) to build distributed photovoltaic projects, according to the non-natural person household photovoltaic record.
(3) If a distributed photovoltaic project is built using a public rental building or a centralized accommodation for foreign talents to live in, and the real estate certificate has not been processed due to historical reasons, the housing ownership certificate shall be issued by the local housing construction department.
2. the grid-connected service process of distributed photovoltaic project construction
1. improve the filing management
(1) the filing information of distributed photovoltaic power generation project shall include the project name, investment subject, construction site, project type, construction scale, online mode, etc. For providing false information, the filing authority may deal with it in accordance with the relevant provisions. For projects that do not conform to the actual situation on site or the filing information and relevant policies, the power supply enterprise shall remind the user to modify the filing information in time. If the user refuses to modify or fails to provide the correct filing certificate within the time limit, the power supply enterprise shall not connect to the grid and terminate the business.
(2) Unless otherwise specified, projects subject to filing management shall be subject to territorial filing in accordance with the ownership of the assets. Cross-district city projects, central enterprises, provincial enterprises, municipal enterprises investment and construction projects refer to Su Zhengfa [2017] No. 88 implementation; the rest of the project by the project location of the county (city, district) record office for the record. For non-natural person household photovoltaic power generation projects, according to the project location of the consolidated filing, the consolidated filing needs to meet the same investment subject, the same filing authority, the construction site, scale and content of a single project clear.
(3) Combined with the actual situation in our city, natural person household photovoltaic power generation projects can be filed by territorial power supply enterprises. The power supply enterprise is responsible for collecting and pushing the filing information according to the relevant filing requirements. The filing authority shall clarify the filing requirements, establish an online filing service mode for natural person household photovoltaic power generation projects, and take the time when the power supply enterprise pushes information as the filing time. If there is any doubt about the data review, the filing authority shall feedback the power supply enterprise within 2 working days. The territorial development and reform department shall do a good job in project filing policy consultation and technical support.
(4) If the natural person household distributed photovoltaic power generation project completed by the power supply enterprise’s agent filing is separately applied to the filing authority for filing due to the natural person’s own reasons, the original agent filing information will automatically become invalid.
(5) power supply enterprises shall do a good job in publicizing the open capacity information of distributed photovoltaic access power grid on a quarterly basis. for areas (including Taiwan areas) that are already in limited access at the time of publicity, the territorial filing authority shall promptly inform and guide the orderly access of distributed photovoltaic power generation projects.
2. reply to grid connection intention
after receiving the letter of intent for grid connection of distributed photovoltaic power generation projects, power supply enterprises shall review relevant materials in a timely manner. If the submitted materials conform to the relevant policies and regulations, a Notice of Acceptance of Intention to Grid Connection of Distributed Photovoltaic Power Generation Projects shall be issued for formal acceptance. For those who do not meet the requirements due to lack of information, a Notice of Intention to Grid Connection of Distributed Photovoltaic Power Generation Projects shall be issued, and the reasons for inadmissibility and additional information shall be notified at one time.
Within the red line of the same land, industrial and commercial distributed photovoltaic power generation projects constructed by stages shall not add new connection points with the public power grid. For projects constructed in phases and filed separately by the same investor, in principle only one power generation account shall be established. For projects constructed in phases and filed separately by different investors, one power generation account may be established; alternatively, separate accounts may be opened after the relevant investors have reached a mutually agreed arrangement for the allocation of generated electricity.
in the acceptance of the net intention to move forward, power supply enterprises should focus on the review of the nature of household distributed photovoltaic property rights, in strict accordance with the nature of property rights classification disposal. For urban residences and rural homesteads with title certificates, they should be handled according to household distributed photovoltaic projects. For the certificate issued by the people’s government of the township (or street) and above, the ownership of the house and the nature of the land residence are clearly defined, the use of the house on site shall be consistent with the nature of the house issued by the certification materials. If there is indeed electricity consumption for production and operation on site, the power supply enterprise shall report to the local competent department and inform the user according to the requirements of general industrial and commercial distributed photovoltaic projects. If the user refuses to modify or fails to provide the correct filing certificate within the time limit, the power supply enterprise shall not connect to the grid and terminate the business.
3. site investigation
the power supply enterprise shall organize and carry out the site investigation according to the time reserved with the customer. during the site investigation, it shall verify whether the project type, construction site attribute, project construction site and other information are consistent with the application data of grid connection intention, and check whether the project starts construction ahead of schedule. If the project starts construction ahead of schedule, the power supply enterprise shall suspend the acceptance of its intention to connect to the grid and report the relevant information to the local competent department for filing.
4. Accept and reply to the report of the access system design scheme
for the natural household distributed photovoltaic power generation project, the power supply enterprise directly replies to the owner of the distributed photovoltaic power generation project according to the typical design scheme.
after receiving the access system scheme design report submitted by the customer, if the integrity and standardization of the content of the access system design report meet the relevant requirements, the power supply enterprise shall issue the acceptance notice of the access system design report; If the requirements are not met due to lack of data, irregular data, etc., the notice of non-acceptance of the access system design report shall be issued. And inform them of the reasons for inadmissibility and the need for supplementary information at one time.
for projects that do not meet the requirements of national and industrial technical standards and specifications, or do not reach an agreement, the power supply enterprise shall specify the opinions of the power supply enterprise and revise and improve the contents in the written reply. after the project investment subject organizes the design unit to revise and improve the access system design scheme, it shall resubmit the access system design scheme to the power supply enterprise. If the customer needs to change the access system design plan report due to his own reasons, the changed access system design plan report shall be submitted to the power supply enterprise, and the follow-up work such as customer engineering construction can be carried out after joint research and approval with the power supply enterprise.
5. contract agreement signing, metering device installation and grid connection inspection
after accepting the grid connection inspection application, the power supply enterprise shall simultaneously carry out grid connection commissioning, metering device installation, contract and agreement signing, and off-grid control and flexible adjustment commissioning. Before the distributed photovoltaic power generation project is connected to the grid, the power supply enterprise shall be responsible for the acceptance of the lines (cables), grid-connected switches, power distribution devices, high-voltage electric energy metering devices, inverters, capacitors, lightning arresters, other electrical equipment test results and qualifications of operators on the user side. If the completion acceptance fails, the project investment entity shall complete the rectification within 4 working days, and fail to complete the rectification within the specified time limit, power supply enterprises shall not be connected to the grid.
6. electricity bill settlement
distributed photovoltaic power generation projects and power supply enterprises must sign electricity purchase and sale contracts before carrying out electricity bill settlement. if no electricity contract is signed, electricity bill settlement shall not be carried out. The cost of electricity generated by the distributed photovoltaic power generation project shall be paid by the main body of the power supply contract. If the payment is not made within the time limit, the power supply enterprise may implement the power outage due in accordance with the law and disconnect the connection point between the photovoltaic project and the power grid side.
3. implement the latest policies
according to the notice requirements of the provincial development and reform Commission, the development and reform departments of each county (city, district) shall, in conjunction with the data department, formulate guidelines for filing matters of distributed photovoltaic power generation projects in their jurisdiction and publish them to the public. The above requirements are inconsistent with the administrative measures for the development and construction of distributed photovoltaic power generation (No.7, 2025) and the implementation opinions on the implementation of the administrative measures for the development and construction of distributed photovoltaic power generation (No.2, 2025), which shall be implemented according to the requirements of the superior documents.